0–30 days
Development of a Conceptual Site Model (CSM) in accordance with DSTU ISO 10381-5:2009 and the LNAPL-3 methodology
Socio-environmental risk assessment identifying contamination pathways and receptors of impact
Development of a strategy to protect people and water resources, focused on addressing specific risks rather than fully remediating the entire area
Coordination of measures to contain the spread of contamination using community, contractor and partner resources
1–24 months
Expert support for communities in preparing a preliminary investment feasibility study and integrating the project into the DREAM ecosystem and Ukraine's green recovery programmes
Organisation of remediation projects using nature-based treatment approaches without excavation of contaminated soils or extraction of groundwater